It's been a busy weekend down at the Cowabunga Bay Construction Site! I took some photos on Saturday & Sunday while Shane, from Cowabunga Bay, sent me some Photos of most of Progress that was made today. With all the excitement growing, and more and more cars driving around looking at Cowabunga Bay, I just wanted to remind everyone that Cowabunga Bay is an Active Construction site and not to Tresspass! There is a Construction Fence there for a Reason.....Your Safety! Now, Onto the Details....

Shane, from Cowabunga Bay, wanted me to thank everyone for their Comments and Suggestions concerning the Prices I posted last week. All of the Feedback has been taken into Consideration for when the Final Prices are posted on CowabungaBay.com and the Cowabunga Bay Construction Blog.

I have recieved many e-mails from people inquiring about Employment Oportunities at Cowabunga Bay and I'm happy to report that the Employment Office Trailer has been delivered to the Construction Site. I will post any and all information regarding Employment, Including the Employment Phone Number, as soon as Shane gives me the go ahead. Keep and eye on the Cowabunga Bay Construction Blog and CowabungaBay.com for that Information, which will be posted soon.

Saturday -
I stopped by the Construction Site on Saturday afternoon to see what progress had been made during the week and was excited to find the construction crew installing sections of Bombora! However, while I was there, the Construction Crew ran into an alignment problem with Bombora that will be worked out in the coming days.

Sunday -
I stopped by the Construction Site on Sunday evening, and found Bombora completed and all of Bonzai finished except the drop and shut down lane.

Monday -
Shane sent me some photos of all the progress that was made today! Shane told me that Bonzai was the First Slide Completed (Slide Entry to Shut Down Lane) at Cowabunga Bay! Bombora is Completed, except for the alignment problem. Hang Ten (Green Slide), Hang Five (Blue Slide), Gremlin (Purple Slide), and Mondo (Magenta Slide) are nearly complete and will be finished by the end of the Week!

- Sid
Cowabunga Bay Construction Blog
cowabungabay@yahoo.com

Check Out the Photos from Today's Cowabunga Bay Construction Update Below:
Cowabunga Bay Construction Update 04/20/2009


The Cowabunga Bay Construction Blog is the Unofficial Blog for Cowabunga Bay Water Park located in Draper, Utah. The Cowabunga Bay Construction Blog is in no way Affiliated with Cowabunga Bay Water Park, Huish Entertainment Group (HEG), or any other Company. All photos property of Cowabunga Bay Construction blog unless otherwise noted and cannot be redistributed without written consent. Copyright 2009 Cowabunga Bay Construction Blog. All Rights Reserved.

No comments: