I have some exciting news, Cowabunga Bay has Gone Vertical! The first sections of the Giant Water Play Structure were lifted into place on the Splash Pad on Monday. Shane from Cowabunga Bay sent some Exclusive Photos from Monday including the Excavated Layout of Cowabunga River, the 400ft Long Lazy River. Shane also posted some of his own Photos on the ThemeParkReview.com Forums. Also, keep an eye on CowabungaBay.com as the New Website will Launch Soon! Lastly, when we have some better weather, we will have another Construction Site Tour with a lot of new photos!

- Sid
Cowabunga Bay Construction Blog
cowabungabay@yahoo.com

Click HERE to view the Construction Photos on ThemeParkReview.com

Exclusive Photos from Cowabunga Bay Below:
Cowabunga Bay Construction Update 03/31/2009


The Cowabunga Bay Construction Blog is the Unofficial Blog for Cowabunga Bay Water Park located in Draper, Utah. The Cowabunga Bay Construction Blog is in no way Affiliated with Cowabunga Bay Water Park, Huish Entertainment Group (HEG), or any other Company. All photos property of Cowabunga Bay Construction blog unless otherwise noted and cannot be redistributed without written consent. Copyright 2009 Cowabunga Bay Construction Blog. All Rights Reserved.

Sunday, March 29, 2009

Cowabunga Bay Construction Update 03/29/2009

Hey Everyone,

I know the Weather has been Horrible with Cold and Snow, but Construction of Cowabunga Bay Continues. More pre assembly of the Giant Water Play Structure has been completed as with Many Footers and the West Side of the Splash Pad. More Structural Components continue to arrive including Support Columns for the Slides and even some Stairs. Hopefully Vertical Construction will begin this Week if the Weather co operates.

- Sid
Cowabunga Bay Construction Blog
cowabungabay@yahoo.com

Cowabunga Bay Construction Update Photos Below:
Cowabunga Bay Construction Update 03/29/2009


The Cowabunga Bay Construction Blog is the Unofficial Blog for Cowabunga Bay Water Park located in Draper, Utah. The Cowabunga Bay Construction Blog is in no way Affiliated with Cowabunga Bay Water Park, Huish Entertainment Group (HEG), or any other Company. All photos property of Cowabunga Bay Construction blog unless otherwise noted and cannot be redistributed without written consent. Copyright 2009 Cowabunga Bay Construction Blog. All Rights Reserved.

Sunday, March 22, 2009

Cowabunga Bay Construction Update 03/22/2009

Hello Everyone,

It's been a busy week down at the Cowabunga Bay Construction Site as Footers were Poured, the Large Crane Assembled, and Construction on Cowabunga River (The Lazy River) & pre assembly of the Giant Water Play Structure began. If the weather co operates, Vertical Construction should begin sometime this Week. We are hoping to have another Construction Site Tour this week as well, so keep an eye out for that.

- Sid
Cowabunga Bay Construction Blog
cowabungabay@yahoo.com

Check Out the Cowabunga Bay Construction Photos Below:
Cowabunga Bay Construction Update 03/21/2009


The Cowabunga Bay Construction Blog is the Unofficial Blog for Cowabunga Bay Water Park located in Draper, Utah. The Cowabunga Bay Construction Blog is in no way Affiliated with Cowabunga Bay Water Park, Huish Entertainment Group (HEG), or any other Company. All photos property of Cowabunga Bay Construction blog unless otherwise noted and cannot be redistributed without written consent. Copyright 2009 Cowabunga Bay Construction Blog. All Rights Reserved.

Friday, March 20, 2009

Cowabunga Bay Construction Update 03/20/2009

Hey Again Everyone,

Shane, from Cowabunga Bay, sent me some New Exclusive Photos including a few of the Water Play Structure Going Vertical in the parking lot. The first footers were poured yesterday and the Large Crane that will place the pre assembled sections of the Water Play Structure has been put together. If everything goes as planned, those pre assembled sections will be placed on the Concrete Slab Monday, officially kicking off Vertical Construction!

- Sid
Cowabunga Bay Construction Blog
cowabungabay@yahoo.com

Check Out the Cowabunga Bay Construction Photos Below:
Cowabunga Bay Construction Update 03/20/2009


The Cowabunga Bay Construction Blog is the Unofficial Blog for Cowabunga Bay Water Park located in Draper, Utah. The Cowabunga Bay Construction Blog is in no way Affiliated with Cowabunga Bay Water Park, Huish Entertainment Group (HEG), or any other Company. All photos property of Cowabunga Bay Construction blog unless otherwise noted and cannot be redistributed without written consent. Copyright 2009 Cowabunga Bay Construction Blog. All Rights Reserved.

Wednesday, March 18, 2009

Cowabunga Bay Construction Update 03/14/2009

Hey Everyone,

I'm sorry this update has taken so long to post, but I promise it won't disappoint. Since the last Construction Update 2 weeks ago, all of the Slides have been pre assembled and more and more Steel Structural Components for the Giant Water Play Structure have arrived at the Construction Site. The Construction Crew has also Covered the Drainage System for the Site and Layed and Covered Pipe for the Water Drains and Water Supply Lines for the Giant Water Play Structure. It looks like Footers for the Giant Water Play Structure are and Construction on the Lazy River are next.

Last Friday, Mike, from CoasterNews.net posted a Construction Update on his website that can be viewed by clicking HERE!

Now, onto reader questions. Many of our Readers have been asking about Employment Opportunities at Cowabunga Bay. Right Now, Cowabunga Bay isn't doing any Hiring but as soon as they are, it will be posted on the Blog. We also recieved a question regarding help with a fund raising Event at a Local School. I am waiting for an answer from Cowabunga Bay as to what Contact Information, if any, I can give out at this time. In the mean time, you can now join Cowabunga's Surfari Club at Cowabungabay.com.

- Sid
Cowabunga Bay Construction Blog
cowabungabay@yahoo.com

Check Out the Cowabunga Bay Construction Photos Below:
Cowabunga Bay Construction Update 03/14/2009



The Cowabunga Bay Construction Blog is the Unofficial Blog for Cowabunga Bay Water Park located in Draper, Utah. The Cowabunga Bay Construction Blog is in no way Affiliated with Cowabunga Bay Water Park, Huish Entertainment Group (HEG), or any other Company. All photos property of Cowabunga Bay Construction blog unless otherwise noted and cannot be redistributed without written consent. Copyright 2009 Cowabunga Bay Construction Blog. All Rights Reserved.

Wednesday, March 4, 2009

Cowabunga Bay Construction Update 03/04/2009

Hey Everyone! I was down in Draper today, and figured I'd stop by the Cowabunga Bay Construction Site and see what was going on. Those of you in Utah know the High Winds we've had Lately and some of the resulting Wind Damage. Unfortunately, the Shelter Cowabunga Bay had built over the Slide Assembly Area was destroyed in the High Winds. Technicians have made quite a bit of Progress on the Body Slides and most Slide Sections of Banzai, Mondo, and Bombora have been Assembled as well as part of the Run Out for Banzai or Mondo. It also appears that Maeday is mostly Completed. Besides some PVC Pipe and an old beat up VW Bug, that's all that's new at the site. Summer just can't get here soon enough!

- Sid Vernon
Cowabunga Bay Construction Blog

Check Out the Photos from Today's Construction Update Below:
Cowabunga Bay Construction Update 03/04/2009


The Cowabunga Bay Construction Blog is the Unofficial Blog for Cowabunga Bay Water Park located in Draper, Utah. The Cowabunga Bay Construction Blog is in no way Affiliated with Cowabunga Bay Water Park, Huish Entertainment Group (HEG), or any other Company. All photos property of Cowabunga Bay Construction blog unless otherwise noted and cannot be redistributed without written consent. Copyright 2009 Cowabunga Bay Construction Blog. All Rights Reserved.